Trans Canada Trail – Phases 2/3 Update

September 7th, 2017|

Construction of the West Bragg Creek Trail (TCT) Phases 2/3 in Rocky View County is expected to be complete by about September 30 for 2017 weather permitting. The trail has 3/4 inch gravel in place...

Trans Canada Trail Construction – Iron Springs

September 2nd, 2017|

This summer our trail construction program is focused on completing the Trans-Canada Trail through West Bragg Creek. The Iron Creek segment has been completed and is ready to use.  The trail continues west from...

Trans Canada Trail Construction 2017

March 27th, 2017|

Trans-Canada Trail (TCT) Phases 2 and 3 In 2016, the Greater Bragg Creek Trails Association (GBCTA) completed phase 1 of the section of the TCT that will link the hamlet of Bragg Creek with trails...